Beta The Briev beta is out. Free on iPhone via TestFlight — install it in under a minute.

Join the beta ↗
Briev
Live
Politics

Audit Finds Kuala Nerus Coastal Erosion Project Lagging 144 Days Over Equipment Shortage and EIA Delays

The Kuala Nerus Coastal Erosion Control Project in Terengganu is running 15.7% behind schedule, delayed by 144 days due to a lack of machinery and postponed Environmental Impact Assessment approval.

In a parliamentary audit tabled today, the Auditor General highlighted a 15.7% delay—equating to 144 days—in the Kuala Nerus Coastal Erosion Control Project in Terengganu. The setback is attributed to a shortage of construction machinery and the contractor’s lag in obtaining Environmental Impact Assessment approval for the beach-nourishment component. Breakwaters numbered 1, 2, 3 and 9 showed no construction progress, prompting calls for stronger coordination between the Public Works Department and the Department of Irrigation and Drainage.

The audit stressed the need to complete Breakwaters 7 and 8 before the upcoming Northeast Monsoon to avoid road collapses on recently repaired sections. Meanwhile, the nationwide Coastal Conservation Programme was praised for completing ten projects that protect vulnerable shorelines and reduce flood risk. The Auditor General’s Report 2/2026 includes fifteen documents covering various government activities.

Why it matters

The delay threatens road stability and coastal protection ahead of the Northeast Monsoon, impacting local communities.

In this story

coastal erosionproject delaymachinery shortageEIA approvalbreakwatersnortheast monsoonaudit findingsbeach nourishment
Get the beta ↗