Mumbai-Goa highway cost surges 48% to Rs 16,909 crore, many sections still unfinished
An RTI obtained by activist Jeetendra Ghadge shows the four-lane Mumbai-Goa highway’s price has risen to Rs 16,909 crore, with Rs 11,577 crore already spent while several stretches remain incomplete.
An RTI filed by activist Jeetendra Ghadge of The Young Whistleblowers Foundation uncovered that the Mumbai-Goa highway project’s total cost has jumped 48% to Rs 16,909 crore, with Rs 11,577 crore already expended on ten four-laning packages. The Parshuram Ghat-Arawali stretch in the Chiplun-Ratnagiri corridor experienced the steepest rise, its sanctioned budget swelling from Rs 983 crore to Rs 2,226 crore, a 126% increase.
Officials cite land acquisition delays, pre-construction setbacks, statutory clearances and contractors’ financial woes as primary causes of the slowdown. The National Highways Authority of India began the Panvel-Indapur segment in 2011, while the Ministry of Road Transport and Highways, via the Maharashtra Public Works Department, started the Indapur-Zarap stretch in 2018. The unfinished sections exacerbate traffic congestion during Ganeshotsav, extending journeys that normally take about seven hours. The Bombay High Court has highlighted the prolonged delays as a hardship for travelers and a fiscal burden on the state.
Why it matters
Rising costs and unfinished work on a major highway strain commuters and public finances.
In this story